EPC Projects

 

Projects under EPC

 

 SL  Name of the Project Length

(Kms)

 Total Project Cost 

(In Rs. Crore)

Status Remarks
 1. Construction of Ganga Path (Digha to Didarganj) at Patna in the State of Bihar on EPC Mode. 21.50 3,160.00 Contractor: M/s Navayuga Engineering Company Ltd.
Authority Engineer : M/s AECOM-RODIC
Appointment Date : 9th Sep. 2013
Completion Date : 8th Sep. 2017

Agreement Amount: Rs. 1,777.40 Crores

Status: Work is in progress.

 Work is in Progress. 
2A. Construction of Elevated Road Corridor from AIIMS to Digha at Patna in the State of Bihar in EPC Mode. 12.27 1,231.06 Contractor : M/s Gammon India Ltd.
Authority Engineer : M/s AECOM-RODIC
Appointment Date : 21 Oct. 2013
Completion Date : 31 March, 2018

Agreement Amount: Rs. 865.17 Crores
Status: Work is in progress.

Work is in Progress.
2B. Construction of South Side Approach Road of Digha Rail-Cum-Road Bridge from AIIMS to Digha (NHAI Leftover Portion)   Contractor : M/s Gammon India Ltd.
Authority Engineer : M/s AECOM-RODIC
Appointment Date : 20 Oct. 2016
Completion Date : 19 April, 2018

Agreement Amount: Rs. 157.14 Crores
Status: Work is in progress.

Work is in Progress.
3. Construction of Greenfield Six-Lane Extradosed Cable Bridge Over river Ganga near Kachchi Dargah in District Patna on NH-30 to near Bidupur in District Vaishali on NH-103. 22.76

(including 9.76 kms

long Main Bridge)

4,988.40 Contractor: M/s Daewoo & L&T (JV)

Agreement Date: 10 Feb, 2016

Agreement Amount: Rs. 3,115.00 Crores

Appointment Date: 16.01.2017

Completion Period: 48 Months

ADB Funding : INR 3,000.00 Cr. (500 M$)

Work is in Progress.

 