 SL  SH No. Length (Kms) Supervision Consultant Name of Civil Worker Contractor Total Project Cost (In Rs. Crore) Agreement Executed On Likely Date of Completion of Project Status Remarks
 1. 68

(Shivganj-Rafiganj-Baidrabad)

82.25

Package-2

South Bihar

Scott Wilson

Contract Price:

US$ 6,50,000+

INR 15,46,42,000

Date of Agreement:

05/12/2008

M/s MBL Infrastructure Ltd., Kolkata 252.38 15.07.2009 31.03.2016 Work in Progress Work in Progress
2. 69

(Dumaria-Sherghati-Ranitalab)

152.80 M/s Gammon India Ltd., Mumbai 442.28 30.12.2008 31.03.2016 Work in Progress Work in Progress
3. 70

(Gaya-Fatehpur-Rajauli)

58.23 M/s Gammon India Ltd., Mumbai 144.19 19.12.2008 Completed Completed Completed
4. 71

(Jehanabad-Ghosi-Rajgir-Parwatipur)

85.20 M/s C&C Construction Ltd., Gurgaon 234.80 24.11.2008 Completed Completed Completed
5. 73

(Siwan-Basantpur-Amnaur-Shitlapur)

88.00

Package-1

North Bihar

ICT-PIDC (JV)

Contract Price:

US $ 13,60,000+

INR 18,83,22,000

Date of Agreement

05/12/2008

GR-JKM (JV) Infra Projects Ltd., New Delhi 290.34 03.07.2009 Completed Completed Completed
6. 74

(Hajipur-Vaishali-Kesharia-Areraj)

87.06 M/s C&C Construction Ltd., Gurgaon 269.28 22.11.2008 Completed Completed Completed
7. 75

(Darbhanga-Kamtaul-Madhwapur)

46.75 M/s IVRCL Infrastructure & Projects Ltd., Hyderabad 211.57 09.07.2009 Completed Completed Completed
8. 76

(Araria-Raniganj-Supaul-Bhaptiyahi)

121.00 M/s BSC-C&C (JV), Gurgaon 436.36 25.11.2008 Completed Completed Completed
9. 77

(Kursela-Sarsi-Raniganj-Forbesganj)

102.93 M/s BSC-C&C (JV), Gurgaon 348.67 25.11.2008 Completed Completed Completed
  TOTAL 824.22     2,629.87        

 

Projects under Implementation in BSHP-II : 5 State Highways (386.675 Kms.) have been placed in BSHP Phase II.

 

 SL  SH No./

Name of Road

Length (Kms) Supervision Consultant Name of Civil Worker Contractor Total Project Cost (In Rs. Crore) Agreement Executed On Likely Date of Completion of Project Status Remarks
 1. Bihta-Daniyawan Section of SH-78

(Bihta Sarmera Road)

100.4 LOA issued to M/s Egis International S.A. in JV Egis India Consulting Engineers Private Limited. Likely to be awarded by 1st week of April, 2016. M/s BSCPL Infrastructure
Ltd., Hyderabad
1117.58 16.07.2015 28.08.2017 Work in Progress After termination in April, 2014, re-bidding of SH-78 splitting in 2 packages done and awarded on 16th July, 2015. Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 391.76 Cr. is Rs. 153.67 Cr. (39.23%).

Chandi-Sarmera Section of SH-78

(Bihta-Sarmera Road)

16.07.2017 11.09.2017 Work in Progress After termination in April, 2014, re-bidding of SH-78 splitting in 2 packages done and awarded on 16th July, 2015. Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 391.76 Cr. is Rs. 153.67 Cr. (39.23%).
2.

Sakkadi-Sahar Section of SH-81 (Sakkadi-Nasriganj Road)

86.8 M/s ICT Pvt.Ltd., New Delhi JV Rodic Consultant Pvt. Ltd, Noida. 
Contract Price: US $16,81,600+
INR 25,44,07,500/-
Date of Agreement: 29.09.2011
M/s BSCPL Infrastructure Ltd., Hyderabad 307.66 10.08.2015 12.10.2017 Work in Progress After termination in September, 2014. Re-bidding of SH-81 splitting in 2 packages done and awarded on 10.08.2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 233.98 Cr. is Rs. 41.25 Cr. (17.63%).
Sahar-Nasriganj Section of SH-81

(Sakkadi-Nasriganj Road)

M/s M.G. Contractors Pvt. Ltd., Haryana 04.07.2015 31.08.2017 Work in Progress After termination in September, 2014. Re-bidding of SH-81 splitting in 2 packages done and awarded on 10.08.2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 233.98 Cr. is Rs. 41.25 Cr. (17.63%).
3. 89

(Siwan-Siswan)

33.065 M/s MSC-C&C JV, Gurgaon 167.96 15.07.2013 30.04.2016 Work in Progress Work in Progress
4.

Mohammadpur-Karankudariya Section of SH-90

(Mohammadpur-Chhapra Road)

64.71 M/s Gawar Construction Ltd., Gurgaon 361.54 24.07.2015 07.11.2017 Work in Progress After termination in April, 2014. Re-bidding of SH-90 splitting in 2 packages done and awarded on 24th July, 2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 201.82 Cr. is Rs. 63.34 Cr. (31.38%).
Karankudariya-Chhapra Section of SH-90 (Mohammadpur-Chhapra Road) M/s Gawar Ceigall (JV), Gurgaon 09.02.2016 20.03.2018 Work in Progress After termination in April, 2014. Re-bidding of SH-90 splitting in 2 packages done and awarded on 24th July, 2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 201.82 Cr. is Rs. 63.34 Cr. (31.38%).
5. 91

(Birpur-Udakishangan)

101.7 M/s Gammon India Ltd., Mumbai 592.27 28.09.2011 22.08.2016 Work in Progress Work in Progress
  TOTAL 386.68     2,547.01        

 

Projects under Implementation in BSHP-II AF: 4 State Highways (253.667 Kms.) have been placed in BSHP Phase II AF.

 

 SL  SH No. Length (Kms) Supervision Consultant Name of Civil Worker Contractor Total Project Cost (In Rs. Crore) Agreement Executed On Likely Date of Completion of Project Status Remarks
 1. 83

(Baghi-Barbigha)

37.646 M/s ICT Pvt.Ltd., New Delhi JV Rodic Consultant Pvt. Ltd, Noida 
Contract Price: US $14,68,400+
INR 21,35,97,500/-
Date of Agreement: 11.04.2013
M/s BSC-C&C JV, Gurgaon 170.32 10.10.2013 28.03.2016 Work in Progress Work in Progress
2. 88

(Baruna Bridge-Rasiyari)

120.354 M/s BSC-C&C JV, Gurgaon 834.47 22.10.2013 28.01.2018 Work in Progress Work in Progress
3. 86

(Saraiya-Motipur)

28.181 M/s Egis International S.A. in JV Egis India Consulting Engineers Pvt. Ltd. in association with Transtek Engineers & Services Pvt. Ltd.
Contract Price: US $7,00,000+
INR 15,99,34,698/-
Date of Agreement: 16.05.2013.
M/s BSC-C&C JV, Gurgaon 210.88 24.09.2013 30.06.2016 Work in Progress Work in Progress
4. 87

(Runnisaidpur-Bhiswa)

67.486 M/s BSC-C&C JV, Gurgaon 443.02 10.10.2013 25.02.2017 Work in Progress Work in Progress
  TOTAL 253.67     1,658.69        

 


Return