Projects under Implementation:

ADB Assisted Bihar State Highways Projects - I, II, II AF; PPP Mode; EPC Mode; JICA Assisted Projects

[BSRDC is also the implementing agency for PPP Mode, EPC Mode and JICA assisted projects in Bihar.]

 

Projects under Implementation in BSHP-I:

9 State Highways (824.22 kms) placed in BSHP Phase-I have been completed.

 

 SL  SH No. Length (Kms) Supervision Consultant Name of Civil Worker Contractor Total Project Cost
(In Rs. Crore)
Agreement
 Executed On 
Status Remarks
 1. 68

(Shivganj-Rafiganj-Baidrabad)

82.25

Package-2

South Bihar

Scott Wilson

Contract Price:

US$ 6,50,000+

INR 15,46,42,000

Date of Agreement:

05/12/2008

M/s MBL Infrastructure Ltd., Kolkata 252.38 15.07.2009  Substantially 
Completed
 Substantially 

Completed

2. 69

(Dumaria-Sherghati-Ranitalab)

152.80 M/s Gammon India Ltd., Mumbai 442.28 30.12.2008  Substantially 
Completed
 Substantially 

Completed

3. 70

(Gaya-Fatehpur-Rajauli)

58.23 M/s Gammon India Ltd., Mumbai 144.19 19.12.2008 Completed Completed
4. 71

(Jehanabad-Ghosi-Rajgir-Parwatipur)

85.20 M/s C&C Construction Ltd., Gurgaon 234.80 24.11.2008 Completed Completed
5. 73

(Siwan-Basantpur-Amnaur-Shitlapur)

88.00

Package-1

North Bihar

ICT-PIDC (JV)

Contract Price:

US $ 13,60,000+

INR 18,83,22,000

Date of Agreement

05/12/2008

GR-JKM (JV) Infra Projects Ltd., New Delhi 290.34 03.07.2009 Completed Completed
6. 74

(Hajipur-Vaishali-Kesharia-Areraj)

87.06 M/s C&C Construction Ltd., Gurgaon 269.28 22.11.2008 Completed Completed
7. 75

(Darbhanga-Kamtaul-Madhwapur)

46.75 M/s IVRCL Infrastructure & Projects Ltd., Hyderabad 211.57 09.07.2009 Completed Completed
8. 76

(Araria-Raniganj-Supaul-Bhaptiyahi)

121.00 M/s BSC-C&C (JV), Gurgaon 436.36 25.11.2008 Completed Completed
9. 77

(Kursela-Sarsi-Raniganj-Forbesganj)

102.93 M/s BSC-C&C (JV), Gurgaon 348.67 25.11.2008 Completed Completed
  TOTAL 824.22     2,629.87      

 

Projects under Implementation in BSHP-II:

5 State Highways (386.675 Kms.) have been placed in BSHP Phase II.

 

 SL  SH No./

Name of Road

Length (Kms) Supervision Consultant Name of Civil Worker Contractor Total Project Cost (In Rs. Crore) Agreement Executed On Likely Date of Completion of Project Status Remarks
 1. Bihta-Daniyawan Section of SH-78

(Bihta Sarmera Road)

100.4 M/s Egis International S.A. in JV Egis India Consulting Engineers Private Limited.
Contract Price: US$ 5,00,000.00 + INR 12,16,23,935.00
Date of Agreement : 31.03.2016
M/s BSCPL Infrastructure
Ltd., Hyderabad
1915.69 16.07.2015 31.12.2018 Work in Progress After termination in April, 2014, re-bidding of SH-78 splitting in 2 packages done and awarded on 16th July, 2015. Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 391.76 Cr. is Rs. 153.67 Cr. (39.23%).

Chandi-Sarmera Section of SH-78

(Bihta-Sarmera Road)

16.07.2015 31.12.2018 Work in Progress After termination in April, 2014, re-bidding of SH-78 splitting in 2 packages done and awarded on 16th July, 2015. Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 391.76 Cr. is Rs. 153.67 Cr. (39.23%).
2.

Sakkadi-Sahar Section of SH-81 (Sakkadi-Nasriganj Road)

86.8 M/s ICT Pvt.Ltd., New Delhi JV Rodic Consultant Pvt. Ltd, Noida
Contract Price: US $1,078,524 +
INR 43,55,92,233/-
Date of Agreement: 29.09.2011
M/s BSCPL Infrastructure Ltd., Hyderabad 535.34 10.08.2015 31.05.2019 Work in Progress After termination in September, 2014. Re-bidding of SH-81 splitting in 2 packages done and awarded on 10.08.2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 233.98 Cr. is Rs. 41.25 Cr. (17.63%).
Sahar-Nasriganj Section of SH-81

(Sakkadi-Nasriganj Road)

M/s M.G. Contractors Pvt. Ltd., Haryana 04.07.2015 31.05.2018 Work in Progress After termination in September, 2014. Re-bidding of SH-81 splitting in 2 packages done and awarded on 10.08.2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 233.98 Cr. is Rs. 41.25 Cr. (17.63%).
3. 89

(Siwan-Siswan)

33.065 M/s BSC-C&C JV, Gurgaon 203.59 15.07.2013 24.06.2016 Work Completed Work Completed
4.

Mohammadpur-Karankudariya Section of SH-90

(Mohammadpur-Chhapra Road)

64.71 M/s Gawar CEIGALL (JV), Gurgaon 504.99 24.07.2015 30.06.2018 Work in Progress After termination in April, 2014. Re-bidding of SH-90 splitting in 2 packages done and awarded on 24th July, 2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 201.82 Cr. is Rs. 63.34 Cr. (31.38%).
Karankudariya-Chhapra Section of SH-90 (Mohammadpur-Chhapra Road) M/s Gawar Ceigall (JV), Gurgaon 09.02.2016 31.05.2018 Work in Progress After termination in April, 2014. Re-bidding of SH-90 splitting in 2 packages done and awarded on 24th July, 2015.
Financial Progress achieved by the previous terminated contractor w.r.t. the previous contract Amount of Rs. 201.82 Cr. is Rs. 63.34 Cr. (31.38%).
5. 91

(Birpur-Udakishanganj)

101.7 M/s Gammon India Ltd., Mumbai 592.27 28.09.2011 31.03.2019 Work in Progress Work in Progress
  TOTAL 386.68     3,751.88        

 

Projects under Implementation in BSHP-II AF:

4 State Highways (253.667 Kms.) have been placed in BSHP Phase II AF.

 

 SL  SH No. Length (Kms) Supervision Consultant Name of Civil Worker Contractor Total Project Cost (In Rs. Crore) Agreement Executed On Likely Date of Completion of Project Status Remarks
 1. 83

(Baghi-Barbigha)

37.646 M/s ICT Pvt.Ltd., New Delhi JV Rodic Consultant Pvt. Ltd, Noida 
Contract Price: US $14,19,208/- +
INR 37,07,46,944/-
Date of Agreement: 11.04.2013
M/s BSC-C&C JV, Gurgaon 235.28 10.10.2013 28.03.2016 Work Completed  Road work Completed. Construction of ROB as an additional work has been started. 
2. Construction of ROB with its approaches in between Km. 11.4 and Km 12.5 of SH-83
(Baghi - Barbigha Road)
  M/s M.G. Contractors

Panchkula, Haryana

26.09.2017 08.01.2019 Work in Progress Work in Progress. EOT in Progress
3. 88

(Baruna Bridge-Rasiyari)

120.354 M/s BSC-C&C JV, Gurgaon 1126.02 22.10.2013 30.09.2019 Work in Progress Work in Progress
4. 86

(Saraiya-Motipur)

28.181 M/s Egis International S.A. in JV Egis India Consulting Engineers Pvt. Ltd. in association with Transtek Engineers & Services Pvt. Ltd.
Contract Price: INR 26,61,06,471/-
Date of Agreement: 16.05.2013.
M/s BSC-C&C JV, Gurgaon 259.01 24.09.2013 16.10.2018 Works substantially completed Works substantially completed
5. 87

(Runnisaidpur-Bhiswa)

67.486 M/s BSC-C&C JV, Gurgaon 551.00 10.10.2013 31.07.2018 Work in Progress Work in Progress
  TOTAL 253.67     2,171.31        

 

Projects under Implementation in BSHP-III:

5 State Highways (231.75 kms) have been placed in BSHP-III (Phase-I):

 

 SL SH No./
Name of Road
 Length

(Kms)

Supervision

Consultant

Name of Civil Works

Contractor

Total Project Cost (A.A.) Agreement

 Executed On

Date of Completion of Project

Remarks

1. 58

(Udakishanganj-Bhatgama Road)

29.48 In Process LOA issued to M/s M. G. Contractors Pvt. Ltd. 234.157 LOA issued to M/s M.G.Contractors Pvt. Ltd. - LOA issued to M/s M. G. Contractors Pvt. Ltd.
2. 84

(Ghogha-Panjwara Road)

43.45 M/s M. G. Contractors, Panchkula, Haryana 376.853 16.11.2018 14.02.2021 Work in Progress
3. 85

(Akbarnagar-Amarpur Road)

29.30   LOA issued to M/s Barbrik-RCPL(JV), Agreement to be signed 220.719 LOA issued to M/s Barbrik-RCPL(JV, Agreement to be signed. - LOA issued to M/s Barbrik-RCPL(JV), Agreement to be signed
4. 82

(Kadirganj-Khaira Road)

75.10 M/s Gayatri Projects Ltd., Hyderabad
 
523.650 21.11.2018 19.02.2021 Work in Progress
5. 102

(Bihia-Jagdishpur-Piro-Bihta Road)

54.52   M/s M. G. Contractors,
Panchkula, Haryana
504.208 23.11.2018 21.02.2021 Work in Progress
Total   231.75      1,859.58      

 